De – Shuttering Period as per IS 456 – 2000

De shuttering period relates to the maturity of concrete and depends on the ambient temperature.

Forms shall not struck until the concrete has reached strength at least twice the stress of which the concrete may be subjected at the time of removal of form work.

FormSummersWinters (Temp <18° C)
Walls, columns and vertical faces of structural members24 hrs.48 hrs.
Removal of props under slab Spanning up to 4.5 m7 days14 days
Removal of props under beams and arches spanning up to 6 m14 days28 days
Soffit form work to slabs 3 days (props to be refixed after removal)
Soffit to beams props 7 days props to refixed after removal.